CEI 0-21 · DM 37/2008
Single-line diagram of a solar PV system. The parts, and the rules that decide them.
The single-line diagram draws the system on one line, from the module to the grid. Here is what goes into it, part by part, and how it changes with the power, with the sources, under Italian rules. In Sunnix Pro the diagram starts from the strings of the quote, and you arrange it like in a CAD.
From the string to the grid
The parts, one by one.
- The stringsModules in series, each on an inverter input (MPPT). Only equal strings go in parallel on the same input.
- The DC sideFor each input the disconnector (it can be the one inside the inverter) and the surge arrester, rated above the string’s open-circuit voltage in the cold (CLC/TS 50539-12, now CLC/TS 51643-32). From 3 strings in parallel, gPV fuses are needed, between 1.5 and 2.4 times the module’s short-circuit current and no higher than the maximum series fuse on its datasheet (IEC TS 62548; ABB QT10).
- The inverterDC below, AC above. The AC line has its circuit breaker, which carries the datasheet’s maximum current (CEI 64-8, art. 433.2) or, without it, the power at a cos φ of 0.9; and its residual current device, type B unless the manufacturer declares that the inverter feeds no DC fault currents (IEC 60364-7-712; EN 62109-1).
- StorageWith a hybrid inverter it is on the DC side, with its own inverter on the AC side. Between the system and the production meter it is “production side”, after it “post production”; if it also charges from the grid, the production meter is bidirectional (GSE technical rules on storage systems, 2021, §4).
- InterfaceThe interface protection (SPI) and the interface device (DDI) disconnect the system from the grid (CEI 0-21). Up to 11.08 kW in total, storage included, and with no more than 3 inverters, they can sit in the CEI 0-21 certified inverter; beyond that they are external, and above 20 kW the DDI has its back-up device.
- General devicesThe general device (DG) after the exchange meter, and the generator device (DDG) on the line of each inverter (CEI 0-21).
- The metersM1 is the exchange meter, the grid operator’s; M2 measures production. Up to 20 kW M2 can be left out if the system pays no excise, enters the market as a single production unit, takes no GSE incentive on the energy produced and shares the connection point with no other unit (ARERA resolution 361/2023).
- The connectionSingle-phase up to 6 kW, up to 10 if the grid operator allows it; beyond that it is three-phase, even with single-phase inverters, with at most 6 kW of imbalance between phases. Up to 100 kW at low voltage, beyond at medium voltage (TICA, art. 2.4), with the substation of CEI 0-16.
kW by kW
How the diagram changes with the power.
Up to 6 kW
Single-phase or three-phase. SPI and DDI can sit in the certified inverter. The installing company’s technical manager can sign it too.
Above 6 and up to 11.08 kW
Three-phase, or single-phase up to 10 kW if the grid operator allows it. SPI and DDI still in the inverter, with no more than 3 inverters. A registered professional signs it.
Above 11.08 and up to 20 kW
SPI and DDI are external, in an interface board. The production meter can be left out, on the conditions of resolution 361/2023.
Above 20 kW
The DDI has its back-up device, and the production meter is always there. Up to 100 kW at low voltage; beyond, at medium voltage, with the substation the designer draws.
Who signs it
Above 6 kW, a registered professional.
- Up to 6 kWThe installing company’s technical manager, or a professional (DM 37/2008, art. 5).
- Above 6 kWA professional registered with their order (DM 37/2008, art. 5; CEI, “Chi può progettare”, 2023; CNI, circular 221/2013).
- At any powerIn an activity subject to Fire Brigade control, the PV design is always signed by a qualified engineer (DCPREV note 14030 of 1 September 2025, §7.1), and so it is in rooms with a higher fire risk or with explosion hazard (DM 37/2008, art. 5, paragraph 2, letter d).
Sources: CEI 0-21 and its FAQ (7 June 2017); TICA, ARERA resolution 99/08; ARERA resolution 361/2023/R/eel; GSE technical rules on storage systems (2021); CEI 64-8; IEC 60364-7-712 and IEC TS 62548 (ABB, technical guide QT10); DM 37/2008, art. 5; DCPREV note 14030 of 2025. Sunnix says what is there: it does not design or sign.
With Sunnix Pro
The diagram, from the strings of the quote.
In Pro the single-line diagram starts from the inverter and the strings saved in the quote, with the rules on this page. It is indicative and in beta: whoever designs it checks and signs it.
- Strings are drawn on the roof or on the field, and the diagram follows them input by input
- You arrange it like in a CAD: move the parts, connect wires between terminals, write notes
- Every rule is checked again at each change, with a one-tap fix
- The A3 PDF, with CEI EN IEC 81346-2 tags, the legend and the title block
From €99 + VAT a month, up to 3 people. 7 days free, no card.
Questions about the PV single-line diagram.
Can’t find the answer? Message us on WhatsApp
The drawing of the system on one line, from the modules to the grid: the strings, the DC protection, the inverter, any storage, the AC protection, the interface (SPI and DDI) and the meters. It is part of the design, and goes with the connection request to the grid operator.
Up to 6 kW also the installing company’s technical manager; above 6 kW a registered professional (DM 37/2008, art. 5). At any power in an activity subject to Fire Brigade control, and in rooms with a higher fire or explosion risk.
Up to 11.08 kW in total, storage included, with no more than 3 inverters and a CEI 0-21 certified inverter. Beyond that they are external, and above 20 kW the DDI has its back-up device.
Above 20 kW, always. Up to 20 kW it can be left out if the system pays no excise, enters the market as a single production unit, takes no GSE incentive on the energy produced and shares the connection point with no other unit (ARERA resolution 361/2023). Systems already installed keep it.
Single-phase up to 6 kW, up to 10 kW if the grid operator allows it. Beyond, three-phase even with single-phase inverters, spread over the phases with at most 6 kW of imbalance.
With a hybrid inverter the battery is on the DC side, with its own inverter on the AC side. If it sits before the production meter and also charges from the grid, the production meter must be bidirectional (GSE technical rules on storage systems, 2021, §4).
An example diagram is not your system’s: modules, inverter and strings change the parts and their ratings. In Sunnix Pro the diagram starts from the quote and is downloaded as an A3 PDF, to be checked and signed.